Nature Plant may be used by you to make smooth wall while maintaining the water absorption and humidity adjustment function of the diatom mud.

Product description

Main components: selected diatomaceous earth, inorganic silicate, nano-polymer material, negative oxygen ion, nano photocatalyst in Asia-Pacific region

Theoretical consumables: natural Yaocao mud (scraping net): 30-35m2/KG; roll coating: 0.2-0.3KG/m2/2 times

Proportion ratio: 2.25KG main material + 0.25KG nano polymer material package + color master: 3.25KG pure water = 1: 1.3

Recoating time (at 25 ° C): surface drying: 2 hours Hard drying: 48 hours Recoating: at least 4 hours apart

Construction tools: laser level, roller, wire mesh, special mold for printing.

Water injection:

1. Inject 3KG water and color masterbatch in the special bucket of Manmu mud and mix well.

2 . Slowly add 2.25KG main material and thicken it at the same time. After stirring for 3-5 minutes, add 0.25KG nano polymer material package.

3 . After about 3-5 minutes, after ensuring uniformity, continue stirring and inject 0.25 KG of water.

Man Tu suggested: according to different processes, increase or decrease the amount of water to adjust the consistency.

Construction method: (select construction method)

A (roller coating): After the water is treated at the bottom of the putty, open the Yao grass mud, apply the light roller evenly twice; apply the dark roller three times, do not polish the last time.

B (scraping net):

1 . Know the construction skills before construction and complete each construction process in strict accordance with the requirements.

2. Customize multiple screens and use laser level for horizontal positioning.

3. Two people work in synchronization, and must clean and air dry after each stripping.

4 . When there is less than one screen positioning on the wall, soft mold construction should be used.

5 . Use a modeling tool to complete the construction of a special process.

Storage: Store in a dry and ventilated place at 20-35 °C. Keep the remaining materials sealed.

Shelf life: 12 months

Precautions:

1. The temperature cannot be started when the temperature is ≤ 5 °C and the relative humidity is ≥ 85%.

2. must be dry and polished during construction, wear a dust mask when polishing the wall.

3. Open all doors and windows to ensure adequate ventilation in the construction area.

4. Read the construction instructions before use to obtain a reliable and satisfactory coating effect.